EPA’s correcting amendment, effective November 3, 2026, sets the emissions-averaging implementation-plan submission deadline at no later than 60 days before the intended compliance demonstration. It applies to lime-manufacturing plants choosing emissions averaging for HCl or mercury. Plans remain subject to review and approval by the applicable regulatory authority; the correction concerns submission timing, not a measured emissions outcome.

Verified facts

  • EPA issued a correcting amendment to the National Emission Standards for Hazardous Air Pollutants for Lime Manufacturing Plants, addressing its technology-review final rule published July 16, 2024.
  • EPA states that the correcting final rule takes effect November 3, 2026.
  • The corrected text requires submission of an emissions-averaging implementation plan no later than 60 days before the date the plant intends to demonstrate compliance using that option.
  • According to EPA, the requirement covers lime plants choosing emissions averaging for HCl or mercury. They must develop and submit the plan to the applicable regulatory authority for review and approval.
  • EPA says the July 16, 2024, final-rule preamble changed the proposed submission deadline from 180 days to 60 days before the compliance demonstration.
  • The corrected provision also requires the implementation plan to contain the information specified in paragraphs (c)(2)(i) through (iii).

Analysis

Release scope: The effective date and the submission deadline serve different purposes. November 3, 2026, is when the correction applies; the 60-day requirement is measured backward from each plant’s intended compliance demonstration. Submission, regulatory review and approval, and the specified plan contents remain distinct elements of the requirement.

Editorial opinion

VERXERA opinion: EPA’s amendment is best understood as a targeted correction to compliance paperwork timing. Effective November 3, 2026, the text uses 60 days before the intended compliance demonstration rather than the 180 days EPA says had been proposed. Read alongside the continuing requirement for regulatory review and approval, that timing change does not mean the plan requirement disappears. This connection matters because the shorter advance-submission period and the obligation to obtain approval describe different parts of the same process. The material limit is its scope: this concerns lime plants selecting emissions averaging for HCl or mercury, not a reported change in emissions. Deeper source reading is most relevant to understanding that option’s plan requirements.

This is VERXERA’s editorial interpretation, separated from the facts and analysis above. The reader keeps the final judgment.

Counterevidence and limits

This report rests on EPA’s correcting amendment; the dates, requirements and account of the earlier deadline are the agency’s statements.

Known uncertainties

The amendment does not identify individual plants’ intended compliance-demonstration dates, so it does not establish their specific calendar submission deadlines.