Key figure: FERC’s notice puts the project’s estimated cost at $46,650,804.
FERC’s notice puts the project’s estimated cost at $46,650,804. Source: federalregister.gov, 2026-11-13. Source: VERXERA card from federalregister.gov

What matters

FERC has announced Equitrans’ request for authorization of the H-320 pipeline in Harrison County, West Virginia, setting a deadline for public participation. Protests, motions to intervene, and comments are due January 8, 2027, at 5:00 p.m. Eastern Time; the notice describes a proposed project, not completed construction.

Verified facts

  • According to FERC, Equitrans filed a prior-notice request on October 28, 2026, in docket CP27-10-000, seeking project authorization under its blanket certificate.
  • FERC describes H-320 as approximately 4.91 miles of 12-inch-diameter pipeline in Harrison County, West Virginia.
  • According to FERC, the pipeline is intended to enable delivery of 108,000 dekatherms per day of natural-gas service to a proposed power plant to be operated by Wolf Summit Energy, LLC.
  • FERC’s notice puts the project’s estimated cost at $46,650,804.
  • FERC set January 8, 2027, at 5:00 p.m. Eastern Time as the deadline for protests, motions to intervene, and comments.
  • FERC says that if no protest is filed within the allowed time, the proposed activity is deemed authorized effective the day after the protest period.
  • FERC says a timely protest withdrawn within 30 days after the protest period also results in deemed authorization effective the day after that period.

Analysis

The FERC notice connects a specific construction proposal with a conditional authorization process. The filing date and participation deadline describe procedural steps. The pipeline dimensions, intended daily gas service, and estimated cost describe the proposal’s scope; they are not measurements of completed construction, operating deliveries, or final spending.

Editorial opinion

VERXERA opinion: The evidence-led conclusion is that this is a consequential project proposal with a defined participation deadline, not a report of operating infrastructure. FERC’s description links approximately 4.91 miles of 12-inch pipeline and an estimated $46,650,804 cost to intended natural-gas service of 108,000 dekatherms per day. Those figures establish the proposal’s physical and financial scale without demonstrating actual deliveries. The January 8, 2027, deadline at 5:00 p.m. Eastern Time matters because FERC describes authorization conditions tied to the protest period. The strongest limitation is that intended service and estimated spending remain proposal figures. Deeper reading of the notice is most relevant to readers assessing the project’s scope or the conditions governing authorization.

This is VERXERA’s editorial interpretation, separated from the facts and analysis above. The reader keeps the final judgment.

Counterevidence and limits

This report rests on FERC’s notice; the project description, estimated cost, and authorization conditions are the agency’s statements.

Known uncertainties

Whether the proposed project proceeds, whether it delivers the intended daily service, and its final cost remain open.